Davyhurst crushing circuit commissioning to start shortly

Davyhurst crushing circuit commissioning to start shortly

Photo by Eastern Goldfields

22nd March 2017

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – Commissioning of the newly refurbished crushing circuit at the Davyhurst mill, in Western Australia, is poised to start next week, with the balance of the circuits expected to be commissioned in April, owner Eastern Goldfields said.

The refurbishment of the 1.2-million-tonne-a-year mill is some 95% complete, with several circuits having been commissioned or nearing completion.

The Davyhurst gold processing plant has been on care and maintenance since 2008, and is being refurbished and recommissioned to process ore from the nearby production sources within the Davyhurst hub.

In addition to the refurbishment work, which started in September last year, Eastern Goldfields is also building a new raw water dam with storage capacity equivalent to seven days of raw water supply, with an upstream tailings lift of the existing tailings storage facility, to provide 12 to 18 months of capacity.

A 5.5 MW containerised diesel-fired power station and a 550 000 ℓ fuel storage facility is also being installed to supplement the existing grid power supply.

Edited by Creamer Media Reporter

Comments

Showroom

SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 
Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.057 0.089s - 90pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: