Construction at True Gold’s Karma almost complete 

11th February 2016

By: Anine Kilian

Contributing Editor Online

  

Font size: - +

JOHANNESBURG (miningweekly.com) – Construction at Toronto-listed gold producer True Gold’s Karma gold mine is 94% complete, with on-site commissioning currently under way, the company reported on Thursday.

In the six months ended December 31, 2015, management forecast that the remaining project spend to completion would be $23.5-million, excluding corporate costs. 

Remaining project costs would be funded by True Gold’s cash position as at December 31, of $5.1-million, $15.4-million remaining on the $100-million Franco-Nevada/Sandstorm gold facility, and a $20-million increase option, of which $5-million was drawn in January 2016. 

To help offset further drawing on the increase option, the company had drawn $6-million of the $10-million available from an equipment refinance facility.

Meanwhile, True Gold revealed that more than 500 000 t of stockpiled ore would be delivered as initial feed to the fully commissioned soft rock crusher, agglomeration and stacking circuit.

Ore had been introduced into the crushing and agglomerating circuits, and agglomerated ore was being stacked on the leach pad. Piping- and solution-collection systems for leach pad cells 1, 2 and 3 had been completed with the installation of the last of the high-density polyethylene lining for the pad-to-pond interface. 

Cell 1 was receiving agglomerated ore, while cells 2 and 3 would be completed in the coming weeks, with final placement of the drainage layer under way.

Construction of the three-process solution ponds – pregnant, intermediate and barren – was complete. They were full of water, with pontoon pumps installed.  

The company also announced that the absorption, desorption and refining plant was nearing completion, with the final installation of piping, electrical and instrumentation remaining. The main construction focus was now on completion of the gold room, where all the equipment in the building was ready to be placed.

Site structural steel work was complete and the remaining civil works were limited to the gold room and to minor infrastructure items.

Further, Phase I of the grade control drilling programme for the Goulagou II pit had been successfully completed and the results were consistent with the anticipated tonnage and grade for the volume drilled.

Phase II of the ongoing programme would start in mid-February.  
 

Edited by Samantha Herbst
Creamer Media Deputy Editor

Comments

Showroom

Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 
GreaseMax
GreaseMax

GreaseMax is a chemically operated automatic lubricator.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Resources Watch
Resources Watch
17th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.152 0.192s - 106pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: