PERTH (miningweekly.com) – Dual-listed coal miner Coalspur has signed a definitive agreement with TSX-listed Canadian National Railway (CN) to transport thermal coal from its Vista project to tidewater.

The seven-year agreement, effective from January this year, and extending through to the end of December 2019, would see CN supplying the equipment to carry Coalspur’s coal from mine site to port.

Some 12-million tons a year of coal would fall under the contract.

Coalspur said on Wednesday that as a result of the contract, the company was able to confirm that its logistics costs for the Vista project would remain as projected, with operating costs estimated at C$56.98/t for the first five years of production, C$59.55/t for the first ten years of production, and C$66.40/t over the life of the mine.

“We are very pleased to have finalised these contracts with CN,” said Coalspur president and CEO Gill Winckler.

“The agreements provide further clarity and stability over our operating costs in the initial years of mining at Vista. Rail and port logistics costs account for around 50% of Coalspur’s free-on-board cash costs, which are now under contracted rates.”

Winckler noted that the company was in the final stages of its detailed negotiations for its funding arrangments for the Vista project, and remained engaged with regulatory agencies to secure regulatory approvals for Phase 1 of the Vista project, which would enable construction to start in the second quarter of this year.

The Vista project was designed to reach a maximum clean coal production rate of 12-million tons a year, and had a life-of-mine expectancy of 29 years. The project would be developed over two phases, with Phase 1 consisting of two discrete stages.

The first stage would produce three-million tons a year of clean coal at a capital cost of approximately C$527-million and the second would provide for a further two-million tons a year of production.

Phase 2 would add an additional seven-million tons a year to take Vista to its maximum design capacity of 12-million tons a year by 2019.

Edited by Creamer Media Reporter

Comments

Showroom

Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 
GreaseMax
GreaseMax

GreaseMax is a chemically operated automatic lubricator.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.133 0.168s - 106pq - 2rq
Subscribe Now