Coal, rapid loadout projects under construction – Exxaro

Exxaro Resources executive head of coal operations Nombasa Tsengwa speaks to Mining Weekly Online’s Martin Creamer, Photographs: Dylan Slater. Video and Video Editing: Darlene Creamer

23rd March 2018

By: Martin Creamer

Creamer Media Editor

     

Font size: - +

Diversified mining company Exxaro Resources, which began a R13-billion coal expansion programme in the second half of last year, has three coal projects and a rapid loadout station under construction, and is at the ready to develop another two coal projects, pending Department of Energy (DoE) and Eskom approval.

The largest of the three coal projects is the R4.8-billion, 1.7-million-tonne-a-year GG6 expansion project at the company's flagship Grootegeluk operation, in Limpopo, where the first semisoft coking coal is expected to be produced in financial year 2020.

The second coal project under construction is the R3.3-billion, 2.7-million-tonne-a-year Belfast coal project, in Mpumalanga, where first production is due in the first half of 2020.

The third coal project under construction, and the one closest to production, is the R600-million Leeuwpan life extension project, also in Mpumalanga, where the first thermal coal is expected before the middle of this year.

Scheduled for commissioning in the first half of next year is the R1.3-billion, 12-million-tonne-a-year Grootegeluk rapid loadout rail station.

The JSE-listed black-led Exxaro is also ready to construct the R3.2-billion first phase of the Thabametsi project, which will have the capacity to produce 3.9-million tonnes of thermal coal a year for a proposed independent power station, as well as the Matla Mine 1 relocation project.

The Thabametsi project is awaiting DoE sanction and construction of the Matla Mine 1 relocation project will start pending approval of State electricity utility Eskom.

A seventh project, which is being commissioned, is the R600-million Grootegeluk discard coal input project.

Exxaro executive head of coal operations Dr Nombasa Tsengwa said the DoE’s notice to proceed for the Thabametsi project was now expected in the second half of this year, with the delay causing the capital expenditure (capex) of the project to increase by a likely R300-million.

No timeframe or delay-induced capex increase was provided for the Eskom-delayed Matla Mine 1, but the company did report that the delay of the diversion of the R50 road did cause the capex of the Leeuwpan life extension project to increase by R78-million.

"As far as our capex spend for 2017 goes, we were R300-million behind," Tsengwa said at the 2017 results presentation, which was attended by Mining Weekly. That was due to the timing of the GG6’s sustaining capex, particularly on the authorisations for the rapid loadout station, as well as the delay of expenditure on the Leeuwpan life extension project.

Owing mainly to the delay of the Thabametsi project, expansion capex for the next five years is up R400-million and sustaining capex of R12.9-billion for the next five years is up R1.46-billion, owing to R900-million being allocated to digitalisation and innovation initiatives.

In response to Mining Weekly, Tsengwa spoke of the unlocking of the Waterberg's “wonderful value” through the GG6 expansion project, where the plant is being rejigged to receive more semisoft coking coal, which has been catered for in long-term rail agreements to transport GG6 production to the Richards Bay Coal Terminal. The rapid loadout station under construction would also end slow train turnaround and penalty risk.

Thabametsi, she said, would be a source of more low-grade coal for power generation and the Belfast coal project a source of high-quality RB1 coal that would complement the company's future product mix positively.

Exxaro CFO Riaan Koppeschaar reported 9% higher revenue of R22.8-billion, mainly on higher Grootegeluk coal volumes and higher prices.

Operating profit was 18% higher at R5.8-billion and 17%-higher core earnings before interest, taxes, depreciation and amortisation, generating cash of R7.2-billion.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

Environmental Assurance (Pty) Ltd.
Environmental Assurance (Pty) Ltd.

ENVASS is a customer and solutions-driven environmental consultancy with established divisions, serviced by highly qualified and experienced...

VISIT SHOWROOM 
Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

PGMs and green hydrogen make headlines
PGMs and green hydrogen make headlines
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.151 0.187s - 88pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: