Carrapateena meets milestone

4th December 2020

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – Copper miner Oz Minerals has completed the ramp-up of its Carrapateena mine, in South Australia, reaching a mine production rate of 4.25-million tonnes a year during November.

“While the mill achieved nameplate capacity in March, the mine production ramp-up has continued throughout the year and has been completed some six months earlier than originally anticipated,” MD and CEO Andrew Cole said on Friday.

“This significant milestone is a credit to all concerned,” he added.

Cole told shareholders that the cave continued to perform well, caving through the upper Whyalla zone on November 27, with the cave now some 260 m from surface, further de-risking the establishment of the cave.

The underground operation is expected to have an estimated mine life of some 20 years, with the project currently estimated to host 950-million tonnes, at 0.57% copper and 0.25 g/t gold for 5.4-million tonnes of contained copper and 7.6-million ounces of gold.

Ore reserves at Carrapateena are estimated at 220-million tonnes, grading 1.1% copper and 0.45 g/t gold for 2.3-million tonnes of contained copper and 3.1-million ounces of gold.

A June prefeasibility study on a block cave expansion of the Carrapateena project, based on the conversion of the lower portion of the current sub-level cave into a series of block caves, found that the expansion would unlock Carrapateena’s potential to be a multi-generational, lowest quartile cash cost producing province.

The study estimated that a capital investment of between A$1.2-billion and A$1.3-billion would be required for the two block caves, with the capital investment weighted towards 2025 to 2027 for surface infrastructure to increase the production rate.


 

Edited by Creamer Media Reporter

Comments

Showroom

John Deere (Pty) Ltd
John Deere (Pty) Ltd

In 1958 John Deere Construction made its first introduction to the industry with their model 64 bulldozer.

VISIT SHOWROOM 
Actom image
Actom

Your one-stop global energy-solution partner

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024
Resources Watch
Resources Watch
17th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.179 0.216s - 94pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: