Blackham gains final approval for Matilda start

14th June 2016

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

  

Font size: - +

JOHANNESBURG (miningweekly.com) – ASX-listed Blackham Resources is on track to start operations at its 4.8-million-ounce Matilda gold project, in Western Australia, in the next quarter, having now gained the final approval required for gold production to start.

Blackham reported on Tuesday that the Department of Mining and Petroleum had granted the Williamson mine mining proposal, following the recent approval of the Matilda mine and Wiluna mining proposals.

The Department of Water had also granted all the water extraction licences, which were needed to begin dewatering the Matilda pits.

As a result of receiving these permits, the A$23-million project facility from Orion Mine Finance had become available, with Blackham having lodged a drawdown notice for A$15-million.

Blackham and Orion had also agreed to extend the expiry term on the facility from August 31, 2018, to February 28, 2019, with repayments to be matched to the gold price and cash flow resulting from the projects.

Blackham reported that the tailings storage facility contractor had mobilised to site and that the openpit and underground mining contractors would mobile to the site later this month.

Gold production would start in the September quarter.

A prefeasibility study in late 2015 found that the Matilda mine would deliver an average 98 000 oz/y over a mine life of nearly five years, at a life-of-mine C1 cash cost of A$920/oz.

Edited by Creamer Media Reporter

Comments

Showroom

Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 
SBS Tanks
SBS Tanks

SBS® Tanks is a leading provider of innovative water security solutions with offices in Southern Africa, East and West Africa, the USA and an...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024
Resources Watch
Resources Watch
17th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.05 0.081s - 90pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: