Bauxite Hill faces delay as enviro rules tighten
PERTH (miningweekly.com) – ASX-listed Metro Mining might face a complicated environmental approvals process at its Bauxite Hills mine, in Queensland.
The miner said on Monday that the Queensland Department of Environment and Heritage Protection (DEHP) had verbally advised the company that they would require a full environmental-impact statement (EIS) for the project, despite already having received a detailed site specific environment authority application.
The company had questioned the validity of the DEHP’s request for the heightened level of environmental scrutiny, pointing out that the Bauxite Hills project did not trigger any of the legislated specific criteria that would require an EIS.
The company further said it had not previously been advised of the need for an EIS, despite being in negotiations with the DEHP since 2014.
“While we have not received formal advice from the department, if that is, in fact, their final position, Metro will seek a formal interdepartmental review through the established process,” the company said in a statement.
Metro added that the company was reviewing its alternative timing strategy for the project.
A February feasibility study estimated that the Bauxite Hills mine would deliver some two-million tonnes a year of direct shipping ore (DSO) product, over a mine life of 21 years.
The DSO operation was expected to require a capital investment of only A$27.4-million and would deliver an internal rate of return of 88% and a net present value after tax of A$197-million.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation