Baobab expansion to cost $53.4m
PERTH (miningweekly.com) – Initial studies into an expanded plant at the Baobab phosphate project, in Senegal, have estimated that the project would require a capital investment of $53.4-million to increase nameplate capacity from the current 500 000 t/y to one-million tonnes a year of high-grade phosphate rock concentrate.
ASX-listed Avenira on Tuesday reported that the expansion should significantly improve product specifications and would place the Baobab project in a globally competitive operating cost position.
The 500 000 t/y processing plant was commissioned in August of last year, with two full cargoes having been sold and shipped since commissioning.
However, Avenira told shareholders that the current processing plant design was considered suboptimal, owing to the simple wet-screening technique employed. This has resulted in low product recovery and high unit operating costs, making the existing operation financially unsustainable in the current price environment.
Avenira undertook a strategic review earlier this year, proposing a significant plant expansion and upgrade to overcome the existing plant’s shortcomings, and to allow the Baobab project to become a key concentrate supplier.
“Now that we have seen the conceptual engineering study results, I am confident that our strategic plan will put Avenira’s Baobab phosphate project on a solid, long-term sustainable footing,” said Avenira MD and CEO Louis Calvarin.
The company will now look to complete engineering and feasibility studies while also securing offtake, approvals and financing for the expansion.
A final investment decision on the expansion was targeted for the second quarter of 2018.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation