Bald Hill lithium plant, Australia

19th January 2018

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Bald Hill lithium plant.

Location
The project area is located 50 km south-east of Kambalda, in the Eastern Goldfields of Western Australia.

Client
Tawana Resources and Alliance Mineral Assets Limited (AMAL).

Project Description
The project comprises four mining leases, one mining lease application, 12 exploration licences, eight prospecting licences and one general purpose lease totalling 790 km.

A July 2017 prefeasibility study (PFS) confirmed the technical and financial viability of a low-capital-cost, 1.2-million-tonne-a-year lithium dense-media separation (DMS) circuit, adjacent to the existing tantalum processing facility at Bald Hill.

The PFS estimates initial production of 155 000 t/y of spodumene concentrate from the DMS and 260 000 lb/y of tantalum pentoxide from the tantalum processing facility. Further feasibility work is being undertaken on a lithium fines circuit to treat stockpiled fines and middlings, which has the potential to add to production.

Potential Job Creation
About 200 people will be on site during the peak construction period.

Net Present Value/Internal Rate of Return
The project has an expected internal rate of return of 185%.

Value
A$42.20-million.

Duration
The first shipment of lithium concentrate is scheduled for March 2018.

Latest Developments
Tawana Resources and AMAL are preparing for the start of lithium concentrate production from Bald Hill during the current quarter.

Tawana MD Mark Calderwood has said that the project is entering “the home straight”, with commissioning expected to start within two months.

The project’s construction and development had been significantly advanced over the past two months, with the DMS plant steelwork installation nearing completion; the piping and electrical cabling advancing; the power station installed and partly commissioned; the run-of-mine pad and crusher pad nearing completion; and mining ramping up, with daily movements reaching 16 000 m3/d.

The first lithium concentrate delivery is expected in April 2018, with the project fully funded to first shipment.

Work on the reserve upgrade is also under way, with the results expected during this quarter.

Key Contracts and Suppliers
Primero Group (EPC).

On Budget and on Time?
The project is on track for commissioning to start in the first quarter of 2018.

Contact Details for Project Information
Tawana investor relations, tel +61 8 9489 2600 or email admin@tawana.com.au.
 
 

Edited by Creamer Media Reporter

Comments

Projects

Showroom

Willard
Willard

Rooted in the hearts of South Africans, combining technology and a quest for perfection to bring you a battery of peerless standing. Willard...

VISIT SHOWROOM 
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)

Education: Consulting with member companies to obtain the optimal benefits from their B-BBEE spending, skills resources as well as B-BBEE points

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.159 0.197s - 90pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: