Bafokeng Rasimone Platinum Mine North Shaft Merensky Phase III project, South Africa
Name of the Project
Bafokeng Rasimone Platinum Mine (BRPM) North Shaft Merensky Phase III project.
Location
North West, South Africa.
Client
BRPM Joint Venture (JV), comprising Royal Bafokeng Platinum (RBPlat) and Anglo American Platinum (Amplats).
Project Description
The BRPM Phase III project is providing further replacement for Merensky production at the North shaft complex through the extension of the existing decline system from Level 10 to Level 15 at the mine boundary.
At steady state, Phase III will maintain the production level of the North shaft at about 100 000 t/m.
Net Present Value/Internal Rate of Return
Not stated.
Value
R1.409-billion.
Duration
The project started in November 2010 and is scheduled for completion in 2018.
Latest Developments
RBPlat reported in its annual report released in February this year that the project at the end of 2016 was 94% complete, with all capital development complete and only the Level 14 and Level 15 construction-related scope, which was deferred to 2017, remaining.
The deferment will have no impact on the mine extraction plan, as project completion remains aligned with the revised project milestone dates.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
The project remains below budget, with expenditure for 2016 amounting to R44-million and R1.04-billion for the project to date.
Contact Details for Project Information
RBPlat executive for corporate affairs Mpueleng Pooe, tel +27 10 590 4515 or
email mpueleng@bafokengplatinum.co.za.
Amplats corporate communications, Mpumi Sithole, tel +27 11 373 6246, fax +27 11 373 5846 or email Mpumi.sithole@angloamerican.com.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation