Atrum improves Groundhog North project economics

20th October 2014

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – Coal developer Atrum Coal has reduced the expected capital cost and increased the mine life of its proposed Groundhog North project, in Canada, after doubling the resource estimate earlier this month.

ASX-listed Atrum on Monday reported that a supplementary prefeasibility study (PFS) into the 5.4-million-tonne-a-year run-of-mine Groundhog North project delivered improved economics of $58-million to deliver a small-scale mining operation.

The projected mine life increased by 138%, from 16 years to 38 years, while the project’s net present value increased by 62%, to A$1.68-billion, and its internal rate of return increased from 39% to 42%.

“The supplementary PFS has delivered outstanding improvements to project economics following our recent resource upgrade at Groundhog North,” said executive chairperson James Chisholm.

The project was estimated to host some 609-million tonnes of resource, including a measured resource of 156-million tonnes, an indicated resource of 193-million tonnes and an inferred resource of 260-million tonnes.

Groundhog North covers less than 5% of Atrum’s broader Groundhog anthracite project, which is estimated to host some 1.57-billion tonnes of resource.

“Subject to permitting, we anticipate our first coal sales in the second half of 2015 from the world’s largest undeveloped ultra-high grade anthracite deposit,” Chisholm added.

Edited by Creamer Media Reporter

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

PGMs and green hydrogen make headlines
PGMs and green hydrogen make headlines
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.171 0.207s - 88pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: